Multifamily residential building in “Druzhba I” district

Year started: 2018 sgrada drujba
Readiness State
Opening of a construction site / Act 2
Excavation activities
Rough construction
Act 14
Finishing works
Exterior facade
Completion of construction / Act 15
Permission for use / Act 16
Share in:

Project’s name:  Multifamily residential building with stores and underground garage

Purpose: Residential building

Number of floors: 5

Location: Sofia city, “Druzhba I”district

Term of completion: 24 months

Project role and type of activity: Investor and head contractor – rough construction, finishing works


There is a catalog with the distribution of the properties on floor levels.